Texaco Barbados
Fabricating and installing 900ft long 8” marine pipeline and
laying three 12,000lb mooring anchors.
1991 Government of Dominica
Fabrication and Installation of 600ft long 8” pipeline and
moorings for Fresh Water exportation project.
1992 Mobil Oil Barbados
Fabricating and installing 8” x 12” lines 1200ft long for oil
importation.
2004 Spent Wash Pipeline
Installed 1200 m of 12” UPVC outfall pipe for rum refinery using Manta Ray anchors ending at 180 ft deep.
2004-05 Government of Barbados
Fabricated and installed three 630 m long steel marine fuel pipelines for Barbados National Oil Terminal Bunkering Facility. Fabricated and installed 180 concrete anchor blocks
and installed and tested all valves and flex lines for pipelines.
|
| Mobil Oil Pipeline |
|
BNTCL Burying Pipeline |
| Launching Flexible
Hose
Deploying Mooring Bouys |
|
| Offshore
Installations
|
|
Mooring
Systems |
|
1989
Texaco St. Kitts
Constructing offshore Dolphin and placing mooring anchors.
2004-05 Commonwealth Construction Ltd.
Fabricated 3 mooring buoys for BNOTCL project as well as Driving five 18 M long x 1M diameter stake piles in water 60-80 feet deep for the Tanker Mooring Facility and installed entire mooring system for 12,000 ton deadweight facility. |
|
|
|